Position compatible tap-offs anywhere along the busway’s continuous plug-in slot, following the selected system’s installation clearances.
Move workstations. Reposition compatible PowerDrops along the existing run as equipment locations change.
Add equipment. Add connections for new machines after reviewing loads and available capacity.
Size the row for your machines. Check the load on each phase when machines run together. Each feed can serve up to 40A per phase on T40 or 225A on T225. Check the largest machine circuit separately. Selected T225 tap-offs handle up to 60A per phase, subject to the breaker and connector ratings. Another feed can serve a separate group of machines. It cannot increase one tap-off’s rating.
Busway and PowerDrops above industrial equipment.
Manufacturing expansion
12 PowerDrops in under an hour with no production downtime
The manufacturer’s in-house facilities team ordered and installed all 12 nine-foot quad PowerDrops on its existing T40 busway. Production kept running while the team added each drop with its tap-off breaker switched off.
“We are looking to get additional power drops for an expansion project that would attach to the existing busway.”Manufacturing engineer
Manufacturing expansion details
The order request specified 12 quad drops with nine-foot cords. USA TrackBusway’s project representative confirmed that the in-house installation took less than one hour and production continued throughout.
The contractor shared its field team’s feedback while discussing a later project.
Customer photo of the workstation installation.
Six more drops for existing workstations
The facility’s own team added four dual-outlet drops and two four-outlet drops to the existing run.
“System is looking great here and love your product.”Facilities manager
Workstation project details
Project drawings helped coordinate support points. The facilities manager supplied the installation photograph and requested pricing for six drops. USA TrackBusway’s project representative confirmed that the customer received and installed all six.
A second warehouse, then 20 more drops
The customer ordered four runs and 24 PowerDrops for its second facility, then added another 20 PowerDrops there.
“All went well they like it & it all went up like you guys said!”Installing contractor, first warehouse installation
Warehouse project details
First installation completed in 2025; second facility supplied in 2026. The later addition of 20 PowerDrops is supported by project/order records and confirmation from USA TrackBusway’s project representative. The contractor’s quote refers to the first installation.
For compatible breakered tap-offs, keep the tap-off breaker OFF during installation or removal until the unit is fully installed and secured. Qualified personnel must follow the applicable installation instructions.
Power for changing production layouts
Plan additions and relocations around available capacity, approved connection positions and the complete equipment schedule.
Machines & Production Cells
Match machine connections to running and starting loads, connector type and approved equipment positions.
Assembly & Work Benches
Place receptacles within reach of tools and bench equipment, with cord routes clear of the work.
Actual R&D workbench installation; customer identity withheld.
Equipment Additions & Layout Changes
Review available capacity before adding equipment. Additional feeds can serve electrically isolated sections; each section retains its own rating.
Watch the 24-second component demonstration to see where the tap-off meets the track. An outlet box keeps the receptacle at the run. A PowerDrop brings it down to the machine.
Plug-in lighting connects to the overhead busway.
Optional lighting that moves with your layout
Compatible lighting plug-ins serve machines and benches alongside equipment power.
Choose compatible task or linear fixtures and follow their installation and relocation instructions.
For a machine with an L16-30P plug, this PowerDrop supplies a 30A circuit through a three-pole breaker and an L16-30R cord-end connector. It carries three phases and ground.
Send the machine schedule and layout, supply voltage and phase, running and starting requirements, plug details, planned additions and required on-site date. Identify support locations, equipment travel paths and environmental conditions for review. Equipment that moves continuously while energized requires a connection designed for that motion; repositionable tap-offs do not make the busway a moving power track.
Evaluate higher aggregate equipment demand against the complete load schedule. Additional feeds serve planned, electrically separate sections; they do not increase an individual section’s rating.
Compare factory busway and conduit for your layout
Start with where power has to go. A plant may use a feeder to reach a production area and a different method to serve the machines along the row.
Approach
When it fits
Conduit
The machine will stay put and its outlet location is known. Price the fixed route to that point.
Fixed-window plug-in busway
Machines can connect at factory-set openings. Check whether the equipment cord can reach an opening at each planned position.
Continuous-access track busway
Machines may move or be added along the row. A compatible tap-off can serve a new position along the existing run. Compare the load on each phase and the largest machine circuit with T40 and T225 ratings.
Feeder busway
The job is to carry bulk power from the source to a downstream distribution point. Evaluate how individual machines will connect beyond that point.
Planning example · One machine moves; the overhead run stays in place
Before · Station A
After · Station B
At Station B, a compatible tap-off serves the machine from the same run. For a new machine or a larger load, check the available capacity and branch protection first.
Compare the same job in each estimate. Use the same route, circuit count and calculated load. Include feeds, supports, installation labor, shutdown windows and access. Price expected moves separately, including spare tap-offs and replacement lead times. Check the proposed assembly against site conditions such as dust, moisture or washdown.
Supply and load: record voltage, phase, current, duty, starting/inrush demand, simultaneous loads and additions. Tap-offs distribute voltage; they do not convert it. A matching 208Y/120V system can provide 120V phase-to-neutral or 208V phase-to-phase. Match 1-pole phase-to-neutral, 2-pole phase-to-phase single-phase, or 3-pole three-phase connections to the load and complete assembly; pole count alone establishes neither voltage nor current rating.
Electrical design: confirm source capacity, feed-section boundaries, phase allocation, available fault current, marked ratings, upstream and branch protection, neutral, grounding and voltage drop. Select the system from the complete load schedule.
Environment and construction: T40 uses 12-gauge steel; T225 uses insulated copper conductors in an aluminum housing. T225 instructions specify indoor, horizontal installation. Identify dust, moisture, washdown, chemicals, corrosion, temperature and hazardous-location classifications. Confirm the exact assembly; an open channel establishes no environmental rating.
Access and support: coordinate approved supports, equipment travel paths, overhead services, connector fit, cord reach/protection and maintenance access. Allow space to insert and secure tap-offs; keep T225 units clear of joints and couplers as instructed.
Installation and changes: qualified personnel must follow the selected system's installation and relocation instructions. T225 inspection, servicing and maintenance require de-energizing, lockout/tagout and verification of absence of voltage.
Optional lighting: use compatible fixtures within circuit capacity, clearance and connection limits. Follow product-specific isolation, breaker-position and relocation instructions.
Qualified personnel must follow the selected system’s current installation and relocation instructions, including required isolation and breaker positions. Lighting and other devices have product-specific requirements. The busway stays fixed.