USA TrackBusway applications

Industrial Overhead Power Distribution

Overhead plug-in power for machines, benches and production cells—built around equipment that changes over time.

Keep power close as work areas change

Position compatible tap-offs anywhere along the busway’s continuous plug-in slot, following the selected system’s installation clearances.

Move workstations. Reposition compatible PowerDrops along the existing run as equipment locations change.

Add equipment. Add connections for new machines after reviewing loads and available capacity.

Size the row for your machines. Check the load on each phase when machines run together. Each feed can serve up to 40A per phase on T40 or 225A on T225. Check the largest machine circuit separately. Selected T225 tap-offs handle up to 60A per phase, subject to the breaker and connector ratings. Another feed can serve a separate group of machines. It cannot increase one tap-off’s rating.

Overhead busway and drop cords in a manufacturing work area
Busway and PowerDrops above industrial equipment.

Manufacturing expansion

12 PowerDrops in under an hour with no production downtime

The manufacturer’s in-house facilities team ordered and installed all 12 nine-foot quad PowerDrops on its existing T40 busway. Production kept running while the team added each drop with its tap-off breaker switched off.

See how the original T40 system shipped in 21 days with paid expediting →

“We are looking to get additional power drops for an expansion project that would attach to the existing busway.”Manufacturing engineer
Manufacturing expansion details

The order request specified 12 quad drops with nine-foot cords. USA TrackBusway’s project representative confirmed that the in-house installation took less than one hour and production continued throughout.

The contractor shared its field team’s feedback while discussing a later project.

Overhead busway and suspended PowerDrops above manufacturing workstations.
Customer photo of the workstation installation.

Six more drops for existing workstations

The facility’s own team added four dual-outlet drops and two four-outlet drops to the existing run.

“System is looking great here and love your product.”Facilities manager
Workstation project details

Project drawings helped coordinate support points. The facilities manager supplied the installation photograph and requested pricing for six drops. USA TrackBusway’s project representative confirmed that the customer received and installed all six.

A second warehouse, then 20 more drops

The customer ordered four runs and 24 PowerDrops for its second facility, then added another 20 PowerDrops there.

“All went well they like it & it all went up like you guys said!”Installing contractor, first warehouse installation
Warehouse project details

First installation completed in 2025; second facility supplied in 2026. The later addition of 20 PowerDrops is supported by project/order records and confirmation from USA TrackBusway’s project representative. The contractor’s quote refers to the first installation.

For compatible breakered tap-offs, keep the tap-off breaker OFF during installation or removal until the unit is fully installed and secured. Qualified personnel must follow the applicable installation instructions.

Power for changing production layouts

Plan additions and relocations around available capacity, approved connection positions and the complete equipment schedule.

Overhead busway with plug-in enclosures and hanging drop cords above equipment stations.

Machines & Production Cells

Match machine connections to running and starting loads, connector type and approved equipment positions.

Cord-fed receptacle boxes serving equipment on an actual research workbench

Assembly & Work Benches

Place receptacles within reach of tools and bench equipment, with cord routes clear of the work.

Actual R&D workbench installation; customer identity withheld.

Overhead busway and plug-in power connections above food-production equipment

Equipment Additions & Layout Changes

Review available capacity before adding equipment. Additional feeds can serve electrically isolated sections; each section retains its own rating.

Overhead plug-in connections serving food-production equipment.

Move power overhead. Bring it to the equipment.

Choose receptacles near the equipment or connections at the overhead run.

Representative T40 PowerDrop cord with tap-off enclosure and cord-end receptacle

PowerDrop Cords

Put receptacles near machines and benches. Select cord reach and connector type for each load.

Explore PowerDrops
Representative T40 120V breakered outlet box mounted beneath Track Busway

Outlet Boxes

Keep receptacle access overhead. Connect equipment cords directly at the busway.

Choose a compatible breakered or unbreakered assembly for the project’s protection arrangement.

Explore outlet boxes

Which T40 connection does the machine need?

Start with the machine’s nameplate and plug. The drawing shows three connections available from a 208Y/120V three-phase T40 run.

  • 120V single-phase: a 1-pole tap-off uses one phase and neutral.
  • 208V single-phase: a 2-pole tap-off uses two phases.
  • 208V three-phase: a 3-pole tap-off uses all three phases.
Compare receptacles for each connection →
T40 wiring and cross sections for 120V single-phase, 208V single-phase and 208V three-phase equipment
Open the full-size T40 diagram ↗

How a tap-off connects to the overhead run

Watch the 24-second component demonstration to see where the tap-off meets the track. An outlet box keeps the receptacle at the run. A PowerDrop brings it down to the machine.

Compatible linear lighting fixture being positioned beneath overhead busway
Plug-in lighting connects to the overhead busway.

Optional lighting that moves with your layout

Compatible lighting plug-ins serve machines and benches alongside equipment power.

Choose compatible task or linear fixtures and follow their installation and relocation instructions.

Explore plug-in linear lighting
Linear lighting fixtures arranged along overhead busway rows
Move compatible fixtures to suit the work below.

Choose your system. Match your tap-offs.

Compare a 120V workstation connection on T40 with a 480V three-phase machine connection on T225.

T40 three-phase double-deck Track Busway length

40A Track Busway (T40)

Up to 40A per phase, per feed.

Single-phase and three-phase configurations for tools, benches and distributed equipment loads.

Explore the 40A system
T40 one-pole breakered PowerDrop with a cord-mounted receptacle

Matching tap-off family

T40 120V PowerDrop

One-pole protection and a cord-mounted receptacle for the T40 system.

View PowerDrop options

Plan your T40 layout in 3D

Explore runs, feeds and matching connections for your layout.

T40 3D configurator preview with busway runs and power connections Open T40 configurator
T225 straight Track Busway length

225A Track Busway (T225)

Up to 225A per phase, per feed.

Higher capacity for equipment rows and zones with greater combined power demand.

Explore the 225A system
T225 three-pole PowerDrop enclosure and drop cord

Machine connection example

T225 480V three-phase PowerDrop

For a machine with an L16-30P plug, this PowerDrop supplies a 30A circuit through a three-pole breaker and an L16-30R cord-end connector. It carries three phases and ground.

View the 30A L16-30R PowerDrop

Plan your T225 layout in 3D

Explore runs, feeds and matching connections for your layout.

T225 3D configurator preview with busway runs and power connections Open T225 configurator

T40 and T225 tap-offs are not interchangeable. Match each tap-off’s current, voltage, receptacle and protection ratings to the load.

Add feeds to electrically isolated sections to expand power across the installation. Each section retains its own rating.

Selected T225 tap-offs support up to 60A per phase across the unit; each output remains limited by its breaker, connector and assembly rating.

Project resources

T40 PowerDrop tap-off and cord

Choose your connections

Match the supply, loads, receptacles and protection to the selected system family.

Buyer’s Guide
T40 installation drawing showing the hanger assembly

Prepare for installation

Review the selected system’s current instructions and project access requirements.

Installation guidance
Project inputs & expansion planning

Send the machine schedule and layout, supply voltage and phase, running and starting requirements, plug details, planned additions and required on-site date. Identify support locations, equipment travel paths and environmental conditions for review. Equipment that moves continuously while energized requires a connection designed for that motion; repositionable tap-offs do not make the busway a moving power track.

Evaluate higher aggregate equipment demand against the complete load schedule. Additional feeds serve planned, electrically separate sections; they do not increase an individual section’s rating.

Review direct-feed and splitter layouts
Compare factory busway and conduit for your layout

Start with where power has to go. A plant may use a feeder to reach a production area and a different method to serve the machines along the row.

ApproachWhen it fits
ConduitThe machine will stay put and its outlet location is known. Price the fixed route to that point.
Fixed-window plug-in buswayMachines can connect at factory-set openings. Check whether the equipment cord can reach an opening at each planned position.
Continuous-access track buswayMachines may move or be added along the row. A compatible tap-off can serve a new position along the existing run. Compare the load on each phase and the largest machine circuit with T40 and T225 ratings.
Feeder buswayThe job is to carry bulk power from the source to a downstream distribution point. Evaluate how individual machines will connect beyond that point.
Planning example · One machine moves; the overhead run stays in place
Before · Station A
After · Station B

At Station B, a compatible tap-off serves the machine from the same run. For a new machine or a larger load, check the available capacity and branch protection first.

Compare the same job in each estimate. Use the same route, circuit count and calculated load. Include feeds, supports, installation labor, shutdown windows and access. Price expected moves separately, including spare tap-offs and replacement lead times. Check the proposed assembly against site conditions such as dust, moisture or washdown.

Compare initial installation and future move costs in the worksheet →

Compare busway architectures and conduit → For equipment that travels while powered, see Track Busway vs. Cable Trolley.

Engineering checks before you specify
  • Supply and load: record voltage, phase, current, duty, starting/inrush demand, simultaneous loads and additions. Tap-offs distribute voltage; they do not convert it. A matching 208Y/120V system can provide 120V phase-to-neutral or 208V phase-to-phase. Match 1-pole phase-to-neutral, 2-pole phase-to-phase single-phase, or 3-pole three-phase connections to the load and complete assembly; pole count alone establishes neither voltage nor current rating.
  • Electrical design: confirm source capacity, feed-section boundaries, phase allocation, available fault current, marked ratings, upstream and branch protection, neutral, grounding and voltage drop. Select the system from the complete load schedule.
  • Environment and construction: T40 uses 12-gauge steel; T225 uses insulated copper conductors in an aluminum housing. T225 instructions specify indoor, horizontal installation. Identify dust, moisture, washdown, chemicals, corrosion, temperature and hazardous-location classifications. Confirm the exact assembly; an open channel establishes no environmental rating.
  • Access and support: coordinate approved supports, equipment travel paths, overhead services, connector fit, cord reach/protection and maintenance access. Allow space to insert and secure tap-offs; keep T225 units clear of joints and couplers as instructed.
  • Installation and changes: qualified personnel must follow the selected system's installation and relocation instructions. T225 inspection, servicing and maintenance require de-energizing, lockout/tagout and verification of absence of voltage.
  • Optional lighting: use compatible fixtures within circuit capacity, clearance and connection limits. Follow product-specific isolation, breaker-position and relocation instructions.

Qualified personnel must follow the selected system’s current installation and relocation instructions, including required isolation and breaker positions. Lighting and other devices have product-specific requirements. The busway stays fixed.

Built-in Flexibility for Your Next Equipment Move

Send your layout, equipment schedule and target date for a coordinated connection plan.

Request industrial layout support