Choose the instructions for your system. T40 and T225 use different feeds, joints and installation hardware. Use the matching installation manual and approved project drawings.
Start with the written instructions for your system; videos illustrate the installation sequence. For project planning, use the T225 submittal checklist to coordinate components and documents.
Press a play button to watch with sound. Use the video controls to pause, adjust volume or view available captions.
T40 · 40A · Steel housing
40A installation
These three steps cover T40 hardware. Installing T225? Use the T225 guide below and its dedicated installation, operation and maintenance manual. Follow the matching manual and approved project drawings.
Our standard installation uses aircraft cable assemblies with self-levelling glides, making it easy to suspend and level USA TrackBusway® runs from almost any structure. If you need a more rigid installation, you can swap the cable for threaded rod using the same hanger body, or you can surface‑mount the busway by bolting the hanger’s top half directly to the structure.
It is the contractor and/or engineer’s responsibility to determine the correct connection to the structure (beam clamp, etc).
With your hangers suspended and adjusted to the correct height, slide each Track Busway length through the hangers to build your run. Align the lengths before tightening the hanger's set screws and trimming the excess cable.
Support Spacing & Hardware Options
Track Busway must be supported within 12 inches of each end and at intervals of no more than 10 feet along the run.
Standard installations use aircraft cable assemblies with self-leveling glides. Where a rigid support method is required, Track Busway may instead be supported from threaded rod (supplied by others) using a barrel nut in place of the cable glide.
Slide the mechanical sleeve over the ends of two adjoining lengths. Each length is electrically independent until you decide to install an electrical insert or add a feed, so you can choose at every sleeve whether to extend a circuit or start a new one.
If you want power to continue through to the next section, align the joiner insert’s center mark with the etched centerline on the sleeve. Turn the first knob, squeeze tightly on the opposite side as illustrated, then turn the second knob to secure the electrical connection. Fully turn one knob in each adjoining length.
If you’re starting a new circuit, leave the insert out and connect a feed unit after the sleeve instead; the built‑in end caps isolate the previous circuit until you add a new feed.
Our line feed houses an integrated breaker and provides knockouts for conduit. Because each Track Busway® length is electrically independent until you choose otherwise, you can install a line feed anywhere along the row.
Align the feed’s busway fitting with the open slot in the Track Busway®. Engage the locking tabs to make the electrical connection, then slide the bolts through the bracket around the fitting to lock the feed mechanically in place.
Once the feed is mechanically secured, connect conduit from your building’s electrical panel through the feed’s knockouts. Land the conductors on the integrated breaker, ground lug and neutral block. After the wiring is complete and the cover is closed, switch on the breaker to energize the busway run.
For the qualified installer: review these points from the T40 instructions alongside the approved project drawings.
Supports: hangers are secured within 12 inches of each run end and no more than 10 feet apart; the lengths are aligned and hanger set screws are tightened.
Joints: end caps are flush and touching inside each sleeve. Sleeve set screws are tightened; where an electrical insert is used, it is centered and both knobs are fully turned, one in each adjoining length.
Feeds: the selected feed matches the layout’s circuit count and deck type.
Breakered PowerDrops: keep the integral breakers OFF throughout installation or relocation. Turn them ON only after the compatible unit is fully installed and securely locked.
Check the supports and alignmentCheck the joint and electrical insert
This summary does not replace the instructions or the project’s testing and commissioning requirements.
T225 · 225A per phase, per feed · Aluminum housing
225A installation
Follow the T225 manual for the complete installation requirements. The clips below illustrate the hardware and sequence; keep the written requirements beside each step.
Installation is for qualified personnel following the current manual, approved project drawings and applicable codes. T225 is for indoor, horizontal installation.
Keep initial busway assembly de-energized. Turn off busway power before installing, removing or working on the end feed, and de-energize upstream power before making feed connections.
Before installing, removing or repositioning a tap-off, set its breaker OFF. Keep it OFF until the unit is completely inserted and securely locked.
For inspection, service and maintenance, de-energize, apply the required lockout/tagout procedure and verify absence of voltage.
Check the actual component labels and selected configuration. Do not install damaged or altered parts, cut or drill housings, or make unapproved substitutions.
Video chapters use overview numbering; this page follows the T225 manual’s step numbers.
T225 suspension hangers engage the upper mounting channel. Follow the support positions and torque specified in the manual.
Press play to watch with sound.
Use approved T225 hangers to secure the first length, then lift and align the next section before joining.
Provide two approved hangers per 10-foot section, a hanger within 12 inches of each end of the continuous run, and no more than 10 feet between adjacent supports. All three requirements apply. Tighten the mounting-channel connection to 24–30 in-lb.
Hanger and mounting-channel connection · Sheet 1, Step 1
The illustrated hanger is attached to 3/8-inch–16 threaded rod. The adjacent view shows a threaded-rod hanger inserted into the top mounting channel. Use the approved hanger arrangement for the project.
Support positions · Sheet 1, Step 1
2T225 · Step 2Complete the mechanical and electrical joint
T225 housing couplers, electrical connector, dedicated installation tool and final joint closure.
Press play to watch with sound.
Align the sections with a gap no greater than 0.25 inch. Fit the housing couplers and center the upper coupler over the joint. Tighten the mechanical joint-coupler fasteners to 8–10 ft-lb; do not exceed 10 ft-lb. Move the lower coupler back to provide access for the electrical connector.
Insert the electrical bus connector into the access slot, center it across the joint and use the specified installation tool to rotate and fully seat it in the busbar channels. Verify full seating before completing mechanical closure. The manual illustrates a 180° tool rotation.
Complete both housing couplers and the electrical connector before energizing, with the final mechanical joint-coupler fasteners at the specified 8–10 ft-lb torque. Do not install a tap-off directly at a joint or housing coupler.
T225 end-feed connection overview. Complete field wiring only with the required isolation and the selected feed’s approved wiring instructions.
Press play to watch with sound.
DANGER—Risk of electric shock or burn. With busway power OFF, install the end feed at the start of the run or where shown on the approved project drawings. De-energize upstream power before making supply connections.
Use the approved wiring diagram, specified 90°C-rated copper conductors, grounding requirements and terminal torques for the selected feed. The manual’s sheet 2 provides the conductor and lug-torque table. Resolve any difference between the selected feed’s markings and the controlled project documents before proceeding.
The animation shows the feed assembly connecting to the busway. Field termination, grounding, isolation and torque checks must be completed from the manual and approved drawings.
These values describe the illustrated configuration. Confirm the selected feed’s markings and approved project wiring diagram before applying them. Resolve any difference before proceeding.
Fit and secure the T225 end cap at the open end of each run. Check that no busway end is left exposed. Confirm the feed cover is also secured before energizing.
Qualified personnel only. Keep the tap-off breaker OFF during installation, removal and relocation; switch ON only after complete insertion and secure locking.
Press play to watch with sound.
Set the tap-off breaker OFF before insertion. Select a position away from joints and housing couplers. Insert the head into the continuous access slot and rotate it to engage the blades.
Tighten the mounting anchor to 24–30 in-lb. Confirm that the unit’s top is flush with the busway bottom, its face is 90° to the run, and the unit is completely inserted and securely locked. Do not switch the breaker ON before these checks are complete.
Tap-off units have no field-wiring terminals. Their cord grips and strain relief are factory installed; do not replace, modify or substitute them in the field.
Complete the T225 manual’s pre-energization checklist. This installation checklist does not replace the project’s commissioning and testing requirements.
Installation is indoors and horizontal.
Two approved hangers are fitted per 10-foot section.
A hanger is within 12 inches of each continuous-run end.
Adjacent supports are no more than 10 feet apart.
Sections are aligned.
Section gaps are no greater than 0.25 inch.
Electrical connectors are fully seated.
Mechanical joint couplers are installed and tightened to 8–10 ft-lb.
Hangers are tightened to 24–30 in-lb.
End-feed conductors match the applicable wiring diagram and every mechanical lug has its specified torque.
Grounding and bonding are complete.
Feed covers and end caps are secured.
Tap-offs are completely inserted and securely locked.
Cord grips and strain relief are secure.
Components are undamaged and have not been field modified.
Required labels are permanent, legible, visible and fitted.
For qualified personnel verifying a T225 outlet-box or PowerDrop connection to a rack PDU before initial energization. Use this checklist with the current T225 manual, selected assembly documentation, rack-PDU instructions and approved project drawings.
Product images show example assemblies. Verify the installed unit’s markings and selected-build documents. The checklist supports initial de-energized commissioning; it is not authorization to perform energized work.
1. Establish safe inspection conditions.
De-energize the busway, follow the applicable lockout/tagout procedure and verify absence of voltage before inspection. Keep the tap-off breaker OFF. Switching that breaker OFF does not establish that the busway is de-energized. Follow the 225A installation guidance.
2. Identify the actual installed assembly.
Record the busway family, tap-off catalog number, marked voltage/current, short-circuit current rating and protective-device configuration. Confirm these match the approved selection and supporting documents. T40 and T225 tap-offs are not interchangeable; the 225A system designation is not the tap-off’s current rating. See the system compatibility guidance.
3. Check the supply, protection and approved loading.
Match the documented supply voltage, phase arrangement and neutral requirement to the rack-PDU input. Verify the selected breaker’s poles, voltage, current and interrupting rating against the approved design. Confirm the load schedule accounts for the applicable continuous-load limits and all outputs sharing the assembly. Use the selected-build ratings guidance.
4. Match the complete connector interface.
For NEMA connections, record the full mating plug/receptacle designation. For IEC 60309 connections, record the manufacturer part numbers, current, voltage, contact arrangement and earth-contact clock position. Check the exact rack-PDU input; appearance or amperage alone does not establish compatibility. Use the NEMA and IEC references.
IEC example. T225 tap box with a 560R6 receptacle, from the existing receptacle guide. Confirm the selected device’s full part number, voltage, current, contact arrangement and clock position.NEMA example. T225 outlet box with an L21-20 receptacle, from the existing receptacle guide. Match the full mating designation and selected assembly ratings to the rack-PDU input.
5. Verify the cord and equipment connection.
Confirm whether the approved connection uses an enclosure-mounted receptacle or a PowerDrop cord connector. Match the cord assembly and mating interface to the PDU manufacturer’s requirements. Check cord condition and secure factory-installed grips and strain relief. Do not modify these components to make a connection fit. See the connection and installation guides.
PowerDrop example. T225 enclosure and cord exit; the cord-end connector is not shown. Verify the actual cord, factory strain relief and mating connector against the approved build.
6. Confirm neutral, grounding and bonding.
Verify that the selected conductor arrangement matches the approved drawings through the feed, busway, joints, tap-off and equipment connection. Where isolated ground is specified, confirm the compatible insulated path while retaining housing grounding. Refer to the grounding and neutral guide.
7. Verify installation and mechanical security.
Confirm the tap-off is away from joints and housing couplers, fully inserted and securely locked. Check its position and mounting-anchor torque against manual Step 5. Confirm there are no damaged, altered or loose components and that required labels are legible. Complete the separate busway pre-energization checklist, including supports, joints, feed connections, grounding, covers and end caps. See the 225A installation checklist.
Installation and locking reference. Existing illustration from the 225A installation guide, corresponding to manual revision 1, sheet 2, Step 5. Open the image to inspect the callouts; follow the complete manual and instructions applicable to the selected assembly.
8. Close outstanding checks before release.
Record completion of the electrical and functional tests required by the applicable manufacturer instructions and approved commissioning plan. Resolve mismatched markings, missing documents, defects and failed checks before energization. Test methods, acceptance limits and the switching sequence must come from those controlled instructions.
Switch the tap-off breaker OFF before releasing it. Loosen and disengage the hanger or lock, rotate the unit out of the slot, and lower it clear. Move it to an allowed position and repeat the Step 5 installation and locking procedure. Keep the breaker OFF until the unit is fully inserted and securely locked.
The manual separately permits qualified personnel to install, remove or reposition compatible breakered T225 tap-offs on an energized busway only with the tap-off breaker OFF and Steps 5 and 6 followed. That limited procedure does not permit under-load insertion or removal, end-feed work, busway-joint work, inspection, service or maintenance on energized equipment.